Photos 11-1-09

|

.............................

Sprinkler pipes painted.




.................................
More pipes painted.

................................
Doors installed

................................
Window trim staining continues.

.........................
Cabinets installed.

...........................


..............................

Photos 11-8-09

|

.............................
Staining of window trim continues.



........................
Stair handrails and plumbing supplies.



...................................
Water fountain and installation location.



................................
Installation of sinks in the bathrooms.



.................................
Toilet installed



........................
Cabinets installed by volunteers.


Photos 10-25-09

|

.............................

Finish work continues.

...........................
Cabinetry arrives, awaiting FMC volunteers for installation.




..............................
Ceiling grid installed.

.............................
Window trim getting ready for stain and finish.

Photos 10-18-09

|

...........................

Tile installation in bathrooms begins

................................



Photos 10-11-09

|

.................................

Trim installation and painting continues

.................................
Furnaces set ready for connection

.............................
More paint and trim work.

....................................
Inside of elevator car.


.................................


........................................
Trim installed on stairs and top of half height wall.
....................................
Finish work continues.

...........................


..................................

Photos 10-4-09

|

...........................
Grass growing in the new landscaped areas.

.....................
Newly planted grass growing well.



Trim boards.

...........................
Trim boards being prepped for installation.

.............................
Furnace room in attic space, Walls are being painted.

..............................
Painting continues on the walls.

Photos 9-27-09

|

..........................
Ceiling stiple work.

..........................
Interior entry doors installed at new entryway.

...........................
Elevator shaft rails and bottom of elevator car.

............................
Elevator control room and access door for elevator car.

........................
Ceiling stiple work being done.

Photos 9-19-09, Drywall finishing.

|

..........................

Sanctuary add on almost done.

..........................
Fourth and fifth grade classrooms.

............................
Third grade and crossing hall second floor.

...............................
MYF room and 2nd floor north hallway.

..............................
Restroom shower and JYF room.

.........................
Back stairs and north hallway.

...........................
Flex classrooms north side.
............................
Cross hall and mechanical room.

................................
Drywall compound application work continues.

..............................
First grade classroom and multipurpose room.

Photos 9-13-09

|

................................
Exterior landscaping and seeding work started.

..............
Rehersal room, drywall compound ready for installation.

....................
Flex class room and entry area.
............................
1st grade room.

..................
2nd Grade and Kindergarten rooms.

..............................
4th and 5th grade rooms and crossing hall ground floor.

.............................
North hall upstairs, North hall ground floor.

............................
Upstairs bathroom with shower and upstairs crossing hall.

......................
JYF room and MYF room.

.....................
Third grade room and hall at the top of the old stairs.

.....................
Drywall work continues.

......................
Expanded Sanctuary nearing completion.

Photos 9-6-09

|


Sprinkler system controls, water supply plumbing


New electrical panel, communications panel.


Drywall installation 2nd grade classroom & hallway.


More drywall, flex classroom and 1st grade.


Drywall new stairwell, kindergarden class.


More drywall elevator shaft and upstairs hallway.


JYF room and upstairs hallway, more drywall.



Soundproof insulation on interior walls.


More drywall installation 4th and 5th Grade classes.

Sprinklers in Fellowship hall.


Sprinkler systems installed in Sanctuary.


New Sanctuary space drywalled.